GEM Engserv Pvt. Ltd is an ISO 9001:2015 certified organization, certified by TUV India in accreditation with National Accreditation Board for Certification Bodies (NABCB).

Concrete blowouts in Post-tension slabs

Bursting of Tendon
HIGHLIGHTS

Post-tensioned (PT) slabs are typically flat slabs, band beam, and slabs or ribbed slabs. PT slabs offer the thinnest slab type, as concrete is worked to its strengths, mostly being kept in compression. Longer spans can be achieved due to prestress, which can also be used to counteract deflections.
Post-tensioned slabs use high-strength tensioned steel strands to compress the slabs, keeping most of the concrete in compression. This gives a very efficient structure that minimizes material usages and decreases the economic span range when compared to reinforced concrete.

Height Comparison of RC & PT Slabs
Height Comparison of RC & PT Slabs

The term pre-stressing is used to describe the process of introducing internal forces (or stress) into a concrete element during the construction process in order to counteract the external loads applied when the structure is put into use (known as service loads). These internal forces are applied by tensioning high-strength steel (generally known as Tendon), which can be done either before or after the concrete is placed. When the steel is tensioned before concrete placement, the process is called pre-tensioning. When the steel is tensioned after concrete placement, the process is called post-tensioning. Because pre-tensioning requires specially designed casting beds, it is generally used in the precast manufacturing process to make simple shapes that can be trucked to a job site. Post-tensioning is done onsite by installing post-tensioning tendons within the concrete formwork in a manner similar to installing rebar.
The most frequent post-tensioning installation problem is listed below

• Strand slippage due to cement paste in the anchor wedge cavity
• Blowout/bursting of concrete and or Tendons
• Tendons too short to be stressed using normal procedures and Tendon splicing.

In this article, the bursting of concrete is discussed as a case study. It is advised that Jobsite troubleshooting should be done only by qualified and experienced personnel.

The case is from a project of 13 floors with the post-tension slab. The grade of concrete for slabs is M40 and the thickness of the slab is 250 mm. The slab is designed with a camber and has a maximum span of 12 m. As per the Structural designer, the slabs must be stressed after achieving the strength of 28 MPa or 70% of concrete strength.

In one of the structure, we had encountered bursting of concrete of slab and tendons while stressing, on more than one occasion. This situation is more probable where very fast cycle times are planned and even a small deviation from best practices can result in bursting in the highly stressed anchorage region. The photos shown below indicate the nature of the problem.

Crack under the anchor head
Crack under the anchor head
Bursting of Tendon
Bursting of Tendon

While it is not very difficult to repair the concrete and carry on with the stressing operations, the situation should be avoided, and the construction process improved to eliminate the root cause.

In order to do that, the concreting and stressing methodology was examined in-depth and the following possible causes were identified:

1. The strength of the concrete specimen may not truly represent the strength in-situ at the anchorage location.
2. Compaction and curing of the concrete in the anchorage location may not be of the highest standard.
3. The sequence of stressing may not have followed the sequence of concreting.
4. There may be a local defect in concrete in the anchorage location.

To eliminate the blowouts in future slabs, the following measures were adopted:
1. Two sets of concrete cubes were sampled in the last 20 to 30 cum of concrete at pouring location on-site in three batches to ascertain the actual strength of in-situ concrete.
2. Special attention was given to compaction of concrete at the anchor locations at the live end while placing of concrete.
3. Before stressing, the side face of the slab was inspected for the formation of cold joints. In case of cold joints, the area was repaired before stressing was allowed to be carried out
4. Stressing sequence was such that the oldest concrete was stresses first (as the pours could stretch for more than 12 hours).
5. Mortar Bunds were provided along the edge of the slab to the extent possible so that curing would cover the edge of the concrete, right till the anchorage.

With these precautions, the instances of the bursting of concrete were completely brought under control and a fast cycle time could be achieved without any interruption.

Subscribe
Notify of
guest
5 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
Redding
August 17, 2020 7:58 am

Interesting to see how the tension can cause strengthening when it comes to concrete. Really had no clue how this worked, but now thanks to your informative article, I have a good idea of how this works. Thanks for sharing, definitely will be reading more often now.

Edward tallabas
Edward tallabas
April 13, 2021 4:53 am

I’m a journeyman concrete guy I’ve seen this before but it’s been a long time it’s concrete you whould think it’s strong and it’s cable and rebar wired

Dipankar ghosh
Dipankar ghosh
April 29, 2021 12:37 pm

Iam a PT Supervisor
From UTRACON in India

KRK
KRK
December 4, 2021 9:25 am

Thanks for sharing valued information about post tensioning slab.We also inspected a PT slab for Waterproofing when examing we noticed lot of crack on top of concrete surface and near tendon area.Site incharge said all cracks happened after stressing of tendons .Then only we came to know ordered RMC was placed after 6hours.. concrete reached site by 9am but placed on slab by 4pm.Here in this case concrete strength has become ?So in post tentioning a high strength concrete is required

Ramesh
Ramesh
May 4, 2023 10:13 pm

this is not a bursting anchor. only crack for this area. this anchor carries the full load, the most thing is after the final stressing it happens during the final stressing it is normal. can u pls give a solution for this one?

WhatsApp Image 2023-05-04 at 3.46.28 PM.jpeg

Liked Reading this Article? Check out below some more similar content..

This article outlines the importance of corrective and preventive action, aside from immediate repairs addressing concrete defects in construction projects.
Aggregates both coarse and fine do not receive the attention that they deserve. Let us understand the contribution of coarse aggregate in concrete.
An interesting thought on "How would concrete on the moon be different from the concrete on the earth?" with intriguing future ready construction technology transformation.
5
0
Would love your thoughts, please comment.x
()
x