GEM Engserv Pvt. Ltd is an ISO 9001:2015 certified organization, certified by TUV India in accreditation with National Accreditation Board for Certification Bodies (NABCB).

Newsletter February 2023

Quality Matters,

So does Engineering Expertise.

FROM THE DIRECTOR'S DESK

It has been observed that the cost of construction of a project is the most important consideration for most clients/project owners. Initially, there is an aspiration in mind. Several interconnected factors in a project charter like the priorities of the client, the intended function of the building/project, site conditions, and location, designer who creates the building design, the method of construction, the choice of procurement options, prevailing market conditions, etc. control the entire cost of a construction project.

Meeting the aspirational cost will be achieved through discussions iterating about the sequence of project charter, design, and costing till the right combination is obtained. Then a rigorous cost control process can be followed where neither aspiration nor cost will be compromised. Project aspiration and project cost must be aligned before taking the go, no-go decision.

This can be done through a good cost consultant and a designer/architect working together to arrive at a correct cost and time for completion. This process may take some time but will be very beneficial for the client/project owner.

ARTICLE FROM THE INDUSTRY EXPERT

This article outlines the importance of corrective and preventive action, aside from immediate repairs addressing concrete defects in construction projects.

PROJECTS WON FOR THE MONTH OF FEBRUARY 2023

Sr. No
Project Name
Client Name
Scope of Work
1
Hub LIC
North Shore Earth Works Inc
Rebar shop drawings
2
Office at Indira Nagar
Godrej Fund Management
Reconciliation of Rebar
3
Fu Shan Public Mortuary at Sha Tin
Vector International Ltd
Rebar detailing
4
Dominican College Extension
Duffy Chartered Engineers
Rebar detailing
5
Sha Tin Sewage treatment works
Vector International Ltd
Quantity & REBAR take off
6
Afrex House
ST1 Group
Quantity take off
7
Institutional Development at Taloja
Pidilite Industries Limited
PMC services
8
Salasakar Park
VST Unity Developers PVT LTD
Planning and Scheduling
9
Dadar building
Vidyalankar Dyanapeeth Trust
Cost to Complete
10
Bridge Design Works
SLNS Earthmovers and Contractors
Bridge Design Works
11
FACT - A, B, C & Heavy Import Cargo building
Mumbai International Airport Ltd (ADANI)
Structural Audit